Project timeline

11/11/2008

Note: The GENSO project is no longer operational.

The project has been running for two years and a proof of concept has been demonstrated. A review and consolidation of requirements and software design is underway and advanced development will soon begin.
The software will be developed according to an evolutionary model with overlapping lifecycle phases and incremental releases. The operational system is due for release to the public in September 2010.

Schedule

 #schedule { background: #fff; padding: 3px; }

Jan-Jun 2007

Preliminary Design and Development Phase

Jul 2007

Preliminary Design Review

Jul-Nov 2007

Preliminary Implementation

Dec 2007-Aug 2008

Core Development and Alpha Testing

Sep 2008-Mar 2009

Consolidation of requirements and software design

Dec 2008-Nov 2009

Advanced Development and Beta Testing

Dec 2009

Critical Design Review

Jan-Mar 2010

Preparation for Network Deployment

Apr 2010

First software release (to limited user group)

Apr-Jul 2010

Enhanced Development and Testing

Aug 2010

Second software release (under public license)

Sep 2010 on

Operational network and ongoing open source development